Bill Wallis Wing: Update 28th January

28th January 2016

It’s been just over two weeks since the last update, and a lot has happened. The roof has been completed so the scaffolding has been taken down, the windows have been installed along with an outside door, and work is now going on inside both old and new buildings.

The walls to the two offices on the far side of Kimber House have been completely smashed through – which surprised everyone this morning when they opened the door that leads to them both, and none more so than Membership Secretary Liz, who has been in her office for six and a half years.